Gill Civil Engineering commenced works at Walney Airfield in Barrow-in-Furness as of November 2018. The scope of works includes the supply and installation of 5240m2 of Reinforced C40/50 Concrete, 175mmdeep. 

The works will be carried out next to a live airfield and involve working around the new hanger and other structures. Despite adverse weather conditions paving and works are on schedule to be completed by January 2019.