Client: Costain Limited
Contract: Felixstowe South Pavement Rehabilitation
Scope of works: Replacement of existing block pavement with pavement quality concrete.
More information:
The Works entail the pavement rehabilitation at the Port of Felixstowe’s South Reconfiguration Phase 1. The works require the removal of part of the existing pavement (pavement blocks) and replacement with pavement quality concrete (PQC) of approximately 100,000m2. The works are to be constructed in 22 major phases with concurrent phases, over a 24 month programme to enable the live port to remain operational throughout the Contract.