Gill Civil delivered pavement rehabilitation and infrastructure upgrades across Taxiway JE-JF and five stands at Manchester Airport, supporting Code C operations while maintaining access throughout complex live-airside works.
As part of the AGL Realigning and Upgrade Programme at Manchester Airport, Gill Civil delivered pavement rehabilitation works to Taxiway JE-JF and Stands 1, 5, 16, 17, and 18, supporting upgrades to Code C. Works included realignment, fuel hydrant relocation, pavement reconstruction, and High Mast Light foundations. Delivered within a live airside environment, the scope included excavation, breakout, reinstatement, and on-site batching for compliant concrete. Works were phased to maintain access, with all concrete tested under UKAS procedures.
Works were delivered within a live airside environment, with challenges including active fuel mains, proximity to terminal buildings, and winter conditions. Pavement over fuel mains required isolation before breakout, with initial sections lifted rather than broken out, adding complexity to sequencing and coordination with MASHCo. Additional constraints included working around High Mast Light foundations and accommodating FEGP and AVDG ducting while maintaining access for aircraft and vehicles. Careful phasing, planning, and use of an on-site batching plant ensured compliant concrete delivery and efficient placement.
The project was delivered on programme, with all PQC and WLC sections meeting airfield performance requirements. On-site batching and phased delivery ensured consistent quality, while careful planning around fuel mains and critical infrastructure minimised disruption. All works were completed under UKAS testing, achieving the required structural integrity. The project demonstrates Gill Civil’s capability to deliver complex live-airside works while maintaining operations and compliance.
Gill Civil delivered airside pavement and drainage works on Taxiway Zulu at Manchester Airport, safely and on schedule, enhancing durability and performance.
Gill Civil delivered urgent pavement reconstruction works across 19 high-risk areas of Manchester Airport’s Alpha Bravo Taxiway, completing the works within restricted night and weekend possessions while maintaining safe airfield operations.
Gill Civil delivered pavement renewal works at Manchester Airport’s Taxiway November Alpha and Stand 112, replacing deteriorated concrete and strengthening critical airside assets while maintaining safe operations within a live airfield environment.