(VLY) Runway Refurbishment

Gill Civil delivered airfield pavement and drainage works at RAF Valley within a four-week shutdown, ensuring durable, high-performance infrastructure and on-time return to operations.

Project Overview and Scope

Gill Civil delivered airfield pavement works at RAF Valley, installing 26,075m² of 260mm Pavement Quality Concrete (PQC) and 150mm Wet Lean Concrete (WLC). The scope also included installation of Gatic slot drainage, V-channel drainage systems, and associated catch pits and outlet chambers. The works formed a key part of the airfield infrastructure upgrade, designed to enhance operational performance and long-term durability.

Challenges and Execution

The majority of works were undertaken during a four-week airfield shutdown (“bolthole”), requiring intensive day and night operations to meet strict programme deadlines. An on-site batching plant was mobilised to ensure continuous concrete supply, maintain quality control, and reduce reliance on external logistics. Careful planning, efficient sequencing, and close coordination enabled delivery within the constrained timeframe while maintaining high safety and quality standards.

Benefits and Outcomes

The scheme was successfully delivered within the restricted shutdown period, ensuring the airfield was returned to full operational use on programme. The completed works provide durable, high-performance pavement and drainage infrastructure, supporting long-term resilience and reliability of the airfield.

OTHER PROJECTS

(MAN) TAXIWAY ZULU

View Project

(MAN) P2P2

View Project

(MAN) PP04 AIRSIDE

View Project

Partner with gill civil on your next project

Simply complete the form and one of our specialists will get back to you as soon as possible to provide the support you need.

Contact Us

Gill House, 140 Holyhead Rd, Birmingham B21 0AF

Plan your Route

Enquire Now

Fill in the form below with your details and queries. A member of our team will reach out to you as soon as possible to discuss your inquiry.